Materials used in London Underground stations and tunnels are assessed against S1085, London Underground’s standard on the fire safety performance of materials in stations and tunnel infrastructure (Issue A5, January 2023). For principal contractors, designers and suppliers, S1085 is often the point where a specification meets procurement, and problems found late are expensive to fix. This note explains what S1085 assesses, where it applies, what it leaves out, and what evidence a compliant submission rests on.

What S1085 assesses

S1085 looks at three fire properties of a material: combustibility, smoke emission and toxic fume emission. It sets its own smoke emission tests rather than relying on the smoke sub-classification within a Euroclass rating. A product with a good Euroclass rating is therefore not automatically compliant: the smoke and toxicity evidence has to be checked as well.

Where it applies

The standard’s scope covers materials in all the locations listed in S1086, London Underground’s classification of stations and shafts. The full set of requirements applies in four situations:

  • at stations covered by the Fire Precautions (Sub-surface Railway Stations) (England) Regulations 2009 and listed in S1086;
  • in running tunnels;
  • at locations that are not effectively separated from those; and
  • where the fire risks are not otherwise controlled to a level as low as reasonably practicable.

“Effectively separated” has a defined meaning. A location qualifies either through fire-resisting construction of the kind S1085 tabulates, with no personnel access through it, or through fire and smoke control supported by the station’s S1080 fire strategy.

An installation that meets the 2009 Regulations does not necessarily comply with S1085. The two are separate tests.

Surface stations are not exempt

A common assumption is that S1085 stops at the sub-surface boundary. It does not. For the public areas of surface stations, S1085 recommends wall and ceiling construction of A2-s3,d2 or better and surface finishes of B-s3,d2 or better, in addition to the Building Regulations requirements (Clause 3.8 a) and b)). BS 9992:2020 Clause 35 recommends the same classes for surface locations.

Stations that are not sub-surface but are enclosed fall under Clause 3.9. S1085 treats a station as enclosed where a public platform and its permanent way are covered continuously for more than 50 m.

What S1085 does not apply to

Clause 3.11 lists items the standard does not apply to. They include:

  • temporary items removed before traffic hours;
  • minor use, up to 100 g or 0.2 m2 of a material;
  • colour variants within a stated colourant limit;
  • materials classified A2-s1,d0 or better;
  • certain materials and enclosures in fire-resisting non-public rooms with London Underground compliant detection; and
  • some portable items, and some public areas such as retail units, where the area has London Underground compliant detection (and, for those public areas, suppression).

Separately, under Clause 3.8 c), items in public and non-public areas of a sub-surface location fitted with London Underground compliant detection and suppression are treated as being in a surface location for materials purposes. Escalator machine chambers are excluded from this, and the wall and ceiling requirement under the 2009 Regulations is preserved.

Each of these has conditions. They are worth reading carefully before a product is ruled out of scope.

What the evidence has to show

S1085 is evidence-led. It expects tests to be carried out by test houses accredited by a national accreditation body, and test reports must be available to London Underground on request. Products are tested in a way that replicates their intended application, including the substrate and mounting, or the result is extended to that application under the direct-application rules of BS EN 13238 or the test laboratory’s field of application. Smoke test results are valid only for the thickness stated in the test report.

Each party contracted to London Underground demonstrates compliance to London Underground, which may audit it. S1085 compliance is not an approval that travels with a product from job to job: each assessment rests on test evidence for the product as it will actually be used. A product accepted on one station can still fail on another if the substrate, thickness or location changes.

In practice, a Materials Compliance Register that records each product, its location, the evidence relied on and the clause it meets is the clearest way to show this, and it is far easier to build at specification stage than at handover.

When a material does not comply

A material that cannot meet S1085 is not resolved by argument in the materials register. Under S1641, London Underground’s standard on concessions, “Concessions are planned or known non-compliance to LU standards.” A material that cannot fully comply needs a concession application under S1641.

How JWCS helps

Where S1085 applies on London Underground premises, we assess materials one product at a time, on per-instance evidence, and record them in the Materials Compliance Register. We review evidence of compliance at specification and procurement stage, flag gaps before products are bought, and support the concession route where a material genuinely cannot comply. More on how we work: S1085 materials compliance and fire systems consultancy.

This note is general guidance for readers working on London Underground projects, not project-specific advice. Check the current issue of S1085 and the requirements of your contract before relying on it.

Related services

  • S1085 Materials Compliance

    Product-by-product S1085 assessment for London Underground stations and tunnels, recorded in a Materials Compliance Register at specification and procurement stage.

  • Fire Systems Consultancy

    Consultancy and assurance across fire systems: active and passive protection, materials compliance, integration and commissioning.

← All insights

Need fire engineering support?

Senior-led from the first conversation.

Contact